Day 25 – 12 Jul 19 – Qala

Day 25 – 12 Jul 19 – Qala

Day 24 and 25 - Two days spent on the consumer unit - yesterday chasing a zillion channels in the wall and today fitting the conduits and running the wiring through to the unit - end result in the images below. 2 days off now before starting again on Monday.  A bit...

Day 23 – 10 Jul 19 – Qala

Day 23 – 10 Jul 19 – Qala

Day 23 - One of those days where, despite working hard all day, not a lot to show for it!  All NeoStat back boxes are now in, the Main Bedroom air condition prep is underway and I spent a lot of time on the floor making multiple holes in walls for conduit and plumbing...

Day 21 – 8 Jul 19 – Qala

Day 21 – 8 Jul 19 – Qala

Day 21 - I've had all those light socket back boxes looking at me empty for the last week or so ....... so today I thought I'd do something about it. All light switches and fittings are now wired!  Slightly harder than wiring the socket points as I had to spend a...

Day 20 – 5 Jul 19 – Qala

Day 20 – 5 Jul 19 – Qala

Day 20 - So today I installed the light and socket fittings on the terrace where I cut the holes for yesterday, stuck up some more fibreglass mesh with render adhesive (getting quite good at that) and ran a couple more cables for lights. Another really hot day today...

Day 18 – 3 Jul 19 – Qala

Day 18 – 3 Jul 19 – Qala

Day 18 - Went and collected all the cables this morning and spent the day running cables through the conduit.  All sockets now have cable in them (bar the one's which will run direct to the consumer unit) and the bathroom light has it's cable in place.  Really pleased...

Day 17 – 2 Jul 19 – Qala

Day 17 – 2 Jul 19 – Qala

Day 17 - I went to the hardware store first thing to buy the electrical cable only to find that I wanted more than they stocked.  So that's ordered for collection tomorrow morning. I decided to make a start applying the insulation's top coat of fibre glass mesh and...

Day 16 – 1 Jul 19 – Qala

Day 16 – 1 Jul 19 – Qala

Day 16 - So, between half a day Saturday and today, all internal electrical back boxes are now complete - just one double waterproof socket and lights on the terrace to go. Tomorrow - off to the shops for around 500 metres of electrical cable and then I'll start...

Day 14 – 28 Jun 19 – Qala

Day 14 – 28 Jun 19 – Qala

Day 14 - A day of 8 double sockets, 1 single socket, 1 junction box and 1 light switch + conduit for the coax cable from the internet provider and bedroom RJ45 high speed internet cables - one of the best days so far in productivity terms. Tomorrow just a half day...

Day 13 – 27 Jun 19 – Qala

Day 13 – 27 Jun 19 – Qala

Day 13 - Completed the sockets and switched in the kitchen area today plus the bathroom light switch.  Also managed to mount the (empty as yet) consumer unit where it can be subsequently hidden by a strategically positioned painting. Tomorrow onto the bathroom (shaver...

Day 12 – 26 Jun 19 – Qala

Day 12 – 26 Jun 19 – Qala

Day 12 - Focussed on the kitchen today to take a bare wall to one having 3 double sockets (above the kitchen worktop), 2 single sockets (up high for Sonos speaker and kitchen cabinet LED lights) and the main kitchen light switch. Tough day as everything needed cutting...

Day 11 – 25 Jun 19 – Qala

Day 11 – 25 Jun 19 – Qala

Day 11 - Worked to 8pm yesterday so didn't blog but happy to report that all electrical socket and switch preparation and conduits to the 3 bedrooms and hallway are now complete. Never in the history of Gozo have so many sockets been installed in bedrooms.  The main...

Day 9 – 22 Jun 19 – Qala

Day 9 – 22 Jun 19 – Qala

Day 9 - Quite a good day apart from the untimely demise of my chaser however I seem to be OK with my trusty angle grinder - German (Bosch) reliability! All chasing is complete in the bedrooms and where there were holes yesterday there's now (in most cases) conduit and...

Day 8 – 21 Jun 19 – Qala

Day 8 – 21 Jun 19 – Qala

Day 8 - not a huge amount achieved today - had to get finished early for another appointment.  Working in bedroom 2, I channelled in a couple of sockets, light switches and light fittings and managed to get another prepared for tomorrow.  Slightly time consuming when...

Day 7 – 20 Jun 19 – Qala

Day 7 – 20 Jun 19 – Qala

Day 7 - Continued with the electrics today.  I got the 3rd bedroom done and finished off (details) the master bedroom.  Installed a socket high up on the wall in the hallway for a speaker and wi-fi extender.  The beauty of finished a shell is that you can build in...

Day 6 – 19 Jun 19 – Qala

Day 6 – 19 Jun 19 – Qala

Day 6 - as promised, cracked on with the electrics today.  Got most of the master bedroom's sockets done + a couple of others as a bonus. It's quite hard work chasing into breeze blocks - very different from limestone as they're hollow and tend to fall apart.  Just...

Day 5 – 18 Jun 19 – Qala

Day 5 – 18 Jun 19 – Qala

Day 5 - not much to report today apart from the spare bedroom and en-suite and the main bathroom are now insulated and I can crack on with electrical trunking tomorrow. Frustrating day - waited around for 2 people scheduled to meet and "no-show".  Still the project...

Day 4 – 13 Jun 19 – Qala

Day 4 – 13 Jun 19 – Qala

Day 4 - and the insulation's almost done!!  The master bedroom is complete (apart from a couple of bottom panels - waiting for the plumbing to go in). The developer's boys are getting on with the rendering in the list shafts - doing a good job too. Next jobs - finish...

Day 3 – 12 Jun 19 – Qala

Day 3 – 12 Jun 19 – Qala

Day 2 - great weather again with that lovely breeze again today for more "insulation sticking". So today I managed to complete the long hallway and get the first panel up in the master bedroom, spend a bit of time with "Michael the Window Guy" talking quotes and took...

Day 2 – 11 Jun 19 – Qala

Day 2 – 11 Jun 19 – Qala

Day 2 - beautiful weather with an amazing breeze flowing through the apartment.  Just continuing on with sticking on insulation panels and buying all the electrical gear (for next week). Biggest challenge is that I have the most amazing view all day which can be quite...

Day 1 – 10 Jun 19 – Qala

Day 1 – 10 Jun 19 – Qala

Day 1 - a bit of a test to see if we could get 2 deliveries and a lifter arriving as planned and promised!  The insulation was to arrive at 09:30am, followed by the bags of adhesive and lifter at 11:00am.  Out of the 3, Noel Vella from J&N Lifting Services was...

From Pallet to Wine Rack

From Pallet to Wine Rack

A left over pallet and a desire for a 16 bottle wine rack and you get the finished article below.  The project took a couple of days in total, finished in coffee stain and Gozitan beeswax with some chalk paint to the sides. I think it looks great .....

Il-Mithna, Qala – 31 May 19

Il-Mithna, Qala – 31 May 19

So, the builders have stated that the 'shell' should be complete by end of next week so I'm gearing up to start work on this penthouse from 10th June 2019. I've put a few marks on the walls for sockets and switches, although the first job that will be done will be...