by admin | 23 Mar 2020 | Air Con, Bathrooms, Finishing Project, Kitchen, Plumbing, Triq Il-Mithna, Qala
The Final Post for this project – a busy 2 weeks which has finalised most of the build. The air conditioning has been installed as has the solar water heating system. 2 of the bathrooms are fully working and the kitchen is complete. The remainder of the work...
by admin | 7 Mar 2020 | Bathrooms, Carpentry, Finishing Project, Light fittings, Plumbing, Render
Days 179 to 183 – a good week in all and still very much on track for moving in by the end of March. The main jobs this week – a water meter/supply is now finally installed. All external waste water pipes have been connected and the walls rendered. The...
by admin | 29 Feb 2020 | Bathrooms, Carpentry, Finishing Project, Grouting, Kitchen, Light fittings, Terrace
Days 174 to 178 – quite a bit achieved this week however slightly deviated from the plan. I wanted to complete connection of all external waste pipes but couldn’t access the light shaft so that’s been delayed. I also wanted to get water mains...
by admin | 22 Feb 2020 | Bathrooms, Circuit Breakers, Finishing Project, Grouting, Kitchen, Terrace, Tiling
Days 165 to 173 – a couple of week’s since my last post so quite a bit achieved, albeit not as much as I anticipated. The terrace which I thought would take 3 or 4 days ended up taking 8, in the main due to time taken mixing concrete. I was adamant that...
by admin | 8 Feb 2020 | Bathrooms, Finishing Project, Grouting, Plumbing, Terrace, Tiling, Triq Il-Mithna, Qala
Days 160 to 164 – This week’s been mainly about the terrace and grouting. The white grouting in 2 bathrooms is complete with about half the master bedroom en-suite done. The terrace is now between 1/3rd and 1/2 done. With help from my friends Laurie, one...
by admin | 1 Feb 2020 | Bathrooms, Finishing Project, Grouting, Kitchen, Triq Il-Mithna, Qala
Days 155 to 159 – Quite a busy week including the application for water and electricity finally made at ARMS! The main tasks this week were painting the terrace walls, installation of the extractor fan and more work done on the kitchen ceiling and grouting which...