Days 160 to 164 – This week’s been mainly about the terrace and grouting.
The white grouting in 2 bathrooms is complete with about half the master bedroom en-suite done. The terrace is now between 1/3rd and 1/2 done. With help from my friends Laurie, one of the bathrooms waste pipes are now complete (connected to the main waste outlets in the utility shaft).
In the common areas, the main stairwell bannister has been installed and the guys from Enemalta have been out to prepare everyone’s metre housings.
Next week the terrace tiling will be completed together with the dark grouting in the bathrooms. Considering not much difference from this week I will probably blog again in a couple of week’s time ….