Days 179 to 183 – a good week in all and still very much on track for moving in by the end of March.

The main jobs this week – a water meter/supply is now finally installed.  All external waste water pipes have been connected and the walls rendered.  The dropped ceiling in the master bedroom en-suite is now complete and the kitchen plumbed in.

Next week the focus will be to get running water throughout the apartment and get at least one bathroom (possibly 2) fully operational.