Days 132 to 136 – Around 4 days worked in total with new year celebrations in the middle.
A week of continued tiling and installing all waste pipes in the 3 toilet areas. These were also weatherproofed when installed. Once tiled, these 3 areas are ready to have their toilets hung.
Next week will be a great one for visual change. A dropped ceiling will be installed in the kitchen ready for the kitchen to be installed on Wednesday. The main bedroom en-suite will also be completed ready for the sink to be installed and toilet to be hung. We will hopefully also get the electricians certificate.
The next 3 week’s will see the flat transform from where it is to “ready to move in”!!