by admin | 10 Aug 2019 | Finishing Project, Floor, Membrane, Triq Il-Mithna, Qala
Days 45 & 46 – the whole floor now has a membrane on it, ready for heating pipe to start being run out on Monday. I’ve also cemented (with a dry mortar) the terrace door step and the kitchen island area, just to ensure we don’t staple pipe in those areas....
by admin | 7 Aug 2019 | Finishing Project, Floor, Membrane, Plumbing, Triq Il-Mithna, Qala, Underfloor Heating
Days 42 to 44 – not quite as planned this week, Monday and Tuesday being spent insulating (against noise) the main bathroom and 3rd bedroom, fitting fibreglass mesh and rendering. Today was spent doing ‘finicky’ jobs – terrace and front door...