by admin | 29 Feb 2020 | Bathrooms, Carpentry, Finishing Project, Grouting, Kitchen, Light fittings, Terrace
Days 174 to 178 – quite a bit achieved this week however slightly deviated from the plan. I wanted to complete connection of all external waste pipes but couldn’t access the light shaft so that’s been delayed. I also wanted to get water mains...
by admin | 22 Feb 2020 | Bathrooms, Circuit Breakers, Finishing Project, Grouting, Kitchen, Terrace, Tiling
Days 165 to 173 – a couple of week’s since my last post so quite a bit achieved, albeit not as much as I anticipated. The terrace which I thought would take 3 or 4 days ended up taking 8, in the main due to time taken mixing concrete. I was adamant that...
by admin | 8 Feb 2020 | Bathrooms, Finishing Project, Grouting, Plumbing, Terrace, Tiling, Triq Il-Mithna, Qala
Days 160 to 164 – This week’s been mainly about the terrace and grouting. The white grouting in 2 bathrooms is complete with about half the master bedroom en-suite done. The terrace is now between 1/3rd and 1/2 done. With help from my friends Laurie, one...