by admin | 12 Jan 2020 | Bathrooms, Carpentry, Finishing Project, Kitchen, Light fittings, Tiling, Triq Il-Mithna, Qala
Days 137 to 142 – A fab week for changes in the apartment. The main event was the delivery and installation of the kitchen (bought in Oct 2018) which looks amazing and totally goes with the floor tiles. Mon and Tue were consumed by fitting the parts of the...
by admin | 5 Jan 2020 | Bathrooms, Finishing Project, Tiling, Triq Il-Mithna, Qala
Days 132 to 136 – Around 4 days worked in total with new year celebrations in the middle. A week of continued tiling and installing all waste pipes in the 3 toilet areas. These were also weatherproofed when installed. Once tiled, these 3 areas are ready to...
by admin | 29 Dec 2019 | Bathrooms, Carpentry, Finishing Project, Plastering, Tiling, Triq Il-Mithna, Qala
Days 128 to 131 – 3.5 days worked this week and a wonderful Christmas enjoyed with family and close friends! The focus on the finishing project has been on the en-suite in the master bedroom. So, the stud wall for the shower cubicle is complete (together with...
by admin | 14 Dec 2019 | Finishing Project, Light fittings, Sockets, Triq Il-Mithna, Qala, Wiring
Days 118 to 122 – so this week’s not been at all glamorous and has been predominantly about lights and lighting circuits. In short – all room lights, bedside lights are now wired and tested/working as are all electrical power sockets. The main...
by admin | 8 Dec 2019 | Bathrooms, Carpentry, Finishing Project, Plumbing, Sockets, Triq Il-Mithna, Qala, Windows, Wiring
Days 111 to 117 – feels like 2 week’s since the last post but with a Valletta mini-break and 2 Wednesday walks only 7 productive days. Still, things are moving on. The MEPA (planning people) compliance certificate has been issued so the main work...