by admin | 24 Jan 2020 | Bathrooms, Finishing Project, Kitchen, Tiling, Triq Il-Mithna, Qala
Days 150 to 154 – All internal tiling (dust creation) is complete! Very happy as a consequence – just the grouting of the wall tiles to go which will be attacked next week. Apart from that this week the frame which will hold the kitchen’s extractor...
by admin | 12 Jan 2020 | Bathrooms, Carpentry, Finishing Project, Kitchen, Light fittings, Tiling, Triq Il-Mithna, Qala
Days 137 to 142 – A fab week for changes in the apartment. The main event was the delivery and installation of the kitchen (bought in Oct 2018) which looks amazing and totally goes with the floor tiles. Mon and Tue were consumed by fitting the parts of the...