Kluvi
  • HOME
  • CONTACT
    • Privacy Policy
  • BLOG
Select Page
German Cottage Refurbishment – 12 Jul to 9th Sep 2021

German Cottage Refurbishment – 12 Jul to 9th Sep 2021

by admin | 22 Sep 2021 | Bathrooms, Carpentry, Chimney, Doorways, Fireplace, German Cottage Refurbishment, Grouting, Kitchen, Light fittings, Render, Tiling

German Country Cottage Refurbishment – 12 Jul to 9 Sep 2021 Our latest project was the refurbishment of a country cottage in the north of Germany, which we managed in 8 weeks.  The 1 bedroom cottage had remained vacant for the previous 18 months and had clearly...
Days Lots!  Weeks of 9th and 16th Mar 2020 – Qala, the final post

Days Lots! Weeks of 9th and 16th Mar 2020 – Qala, the final post

by admin | 23 Mar 2020 | Air Con, Bathrooms, Finishing Project, Kitchen, Plumbing, Triq Il-Mithna, Qala

The Final Post for this project – a busy 2 weeks which has finalised most of the build. The air conditioning has been installed as has the solar water heating system.  2 of the bathrooms are fully working and the kitchen is complete. The remainder of the work...
Days 174 to 178 – week of 24th Feb 2020 – Qala

Days 174 to 178 – week of 24th Feb 2020 – Qala

by admin | 29 Feb 2020 | Bathrooms, Carpentry, Finishing Project, Grouting, Kitchen, Light fittings, Terrace

Days 174 to 178 – quite a bit achieved this week however slightly deviated from the plan.  I wanted to complete connection of all external waste pipes but couldn’t access the light shaft so that’s been delayed.  I also wanted to get water mains...
Days 165 to 173 – weeks of 10 & 17 Feb 2020 – Qala

Days 165 to 173 – weeks of 10 & 17 Feb 2020 – Qala

by admin | 22 Feb 2020 | Bathrooms, Circuit Breakers, Finishing Project, Grouting, Kitchen, Terrace, Tiling

Days 165 to 173 – a couple of week’s since my last post so quite a bit achieved, albeit not as much as I anticipated. The terrace which I thought would take 3 or 4 days ended up taking 8, in the main due to time taken mixing concrete.  I was adamant that...
Days 155 to 159 – week of 27th Jan 2020 – Qala

Days 155 to 159 – week of 27th Jan 2020 – Qala

by admin | 1 Feb 2020 | Bathrooms, Finishing Project, Grouting, Kitchen, Triq Il-Mithna, Qala

Days 155 to 159 – Quite a busy week including the application for water and electricity finally made at ARMS! The main tasks this week were painting the terrace walls, installation of the extractor fan and more work done on the kitchen ceiling and grouting which...
« Older Entries

Recent Posts

  • German Cottage Refurbishment – 12 Jul to 9th Sep 2021
  • Days Lots! Weeks of 9th and 16th Mar 2020 – Qala, the final post
  • Days 179 to 183 – week of 2nd March 2020 – Qala
  • Days 174 to 178 – week of 24th Feb 2020 – Qala
  • Days 165 to 173 – weeks of 10 & 17 Feb 2020 – Qala

Categories

  • Air Con
  • Bathrooms
  • Carpentry
  • Chimney
  • Circuit Breakers
  • Doorways
  • Finishing Project
  • Fireplace
  • Floor
  • Floor screed
  • German Cottage Refurbishment
  • Grouting
  • Insulation
  • Kitchen
  • Light fittings
  • Membrane
  • Pallet to Wine Rack
  • Plastering
  • Plumbing
  • Render
  • Roof
  • Skylight
  • Sockets
  • Terrace
  • Tiling
  • Triq Il-Mithna, Qala
  • Underfloor Heating
  • Window Sills
  • Windows
  • Wiring
Copyright © 2024 Kluvi - all rights reserved.