by admin | 5 Jan 2020 | Bathrooms, Finishing Project, Tiling, Triq Il-Mithna, Qala
Days 132 to 136 – Around 4 days worked in total with new year celebrations in the middle. A week of continued tiling and installing all waste pipes in the 3 toilet areas. These were also weatherproofed when installed. Once tiled, these 3 areas are ready to...
by admin | 29 Dec 2019 | Bathrooms, Carpentry, Finishing Project, Plastering, Tiling, Triq Il-Mithna, Qala
Days 128 to 131 – 3.5 days worked this week and a wonderful Christmas enjoyed with family and close friends! The focus on the finishing project has been on the en-suite in the master bedroom. So, the stud wall for the shower cubicle is complete (together with...
by admin | 22 Dec 2019 | Bathrooms, Carpentry, Circuit Breakers, Finishing Project, Plumbing, Roof, Skylight, Sockets, Wiring
Days 123 to 127 – I didn’t think there was much to report this week until I looked back through the photo’s which show that we had a fab and busy week! Monday saw a respite in the weather (wind) so Michael and I managed to get the skylight...
by admin | 8 Dec 2019 | Bathrooms, Carpentry, Finishing Project, Plumbing, Sockets, Triq Il-Mithna, Qala, Windows, Wiring
Days 111 to 117 – feels like 2 week’s since the last post but with a Valletta mini-break and 2 Wednesday walks only 7 productive days. Still, things are moving on. The MEPA (planning people) compliance certificate has been issued so the main work...
by admin | 23 Nov 2019 | Bathrooms, Carpentry, Finishing Project, Tiling, Triq Il-Mithna, Qala
Days 106 to 110 – another busy week – no work Wednesday and half a day today but quite a bit done. The tiling of the rear balcony is complete bar for grouting (next week). The tiling of the guest en-suite has continued and is looking great. I’ve...