by admin | 16 Nov 2019 | Bathrooms, Finishing Project, Grouting, Tiling, Triq Il-Mithna, Qala
Days 102 to 105 – An interesting week with force 8/9 gales and no windows! Only 4 days worked due to me walking on Wednesday and a guest. However, a busy week. Last weekend we visited the window builder and saw the windows and rear balcony railing. The...
by admin | 2 Nov 2019 | Bathrooms, Finishing Project, Grouting, Plumbing, Tiling
Days 92 to 96 – I took Wednesday off to join the Gozo Wednesday Walkers – something I’ll try and do more frequently going forward. Another busy week in the flat – the weather didn’t permit any further work on the roof so the focus was on...