Days 42 to 44 – 5 to 7 Jul 2019 – Qala

Days 42 to 44 – 5 to 7 Jul 2019 – Qala

by admin | 7 Aug 2019 | Finishing Project, Floor, Membrane, Plumbing, Triq Il-Mithna, Qala, Underfloor Heating

Days 42 to 44 – not quite as planned this week, Monday and Tuesday being spent insulating (against noise) the main bathroom and 3rd bedroom, fitting fibreglass mesh and rendering.  Today was spent doing ‘finicky’ jobs – terrace and front door...

Recent Posts

  • German Cottage Refurbishment – 12 Jul to 9th Sep 2021
  • Days Lots! Weeks of 9th and 16th Mar 2020 – Qala, the final post
  • Days 179 to 183 – week of 2nd March 2020 – Qala
  • Days 174 to 178 – week of 24th Feb 2020 – Qala
  • Days 165 to 173 – weeks of 10 & 17 Feb 2020 – Qala

Categories

  • Air Con
  • Bathrooms
  • Carpentry
  • Chimney
  • Circuit Breakers
  • Doorways
  • Finishing Project
  • Fireplace
  • Floor
  • Floor screed
  • German Cottage Refurbishment
  • Grouting
  • Insulation
  • Kitchen
  • Light fittings
  • Membrane
  • Pallet to Wine Rack
  • Plastering
  • Plumbing
  • Render
  • Roof
  • Skylight
  • Sockets
  • Terrace
  • Tiling
  • Triq Il-Mithna, Qala
  • Underfloor Heating
  • Window Sills
  • Windows
  • Wiring
Copyright © 2024 Kluvi - all rights reserved.