Days 39 to 41 – 31 Jul to 2 Aug 19 – Qala

Days 39 to 41 – 31 Jul to 2 Aug 19 – Qala

by admin | 3 Aug 2019 | Finishing Project, Floor, Triq Il-Mithna, Qala

Days 39 to 41 – 3 days working away on floor insulation in the open plan area, bathroom and guest bedroom en-suite. Next week, the membrane will go down (Mon/Tue), the manifold loosely fitted the the wall and we’ll start running out underfloor heating pipe...
Days 37 & 38 – 29/30 Jul 19 – Qala

Days 37 & 38 – 29/30 Jul 19 – Qala

by admin | 30 Jul 2019 | Finishing Project, Floor, Triq Il-Mithna, Qala

Days 37 & 38 – So yesterday half the tiles arrived and my good friend Laurie Xuereb helped me lifting them onto the terrace.  Continued and completed the guest bedroom and today completed the 3rd bedroom and worked on the floor in the kitchen and sitting...
Days 34 to 36 – 24 to 26 Jul 19 – Qala

Days 34 to 36 – 24 to 26 Jul 19 – Qala

by admin | 26 Jul 2019 | Finishing Project, Floor, Triq Il-Mithna, Qala

Days 34 to 36 – The last 3 days have been all about the floor – from getting a mountain of sand delivered to laying the floor insulation ontop of which the underfloor heating pipes will sit. The hallway and main bedrooms are now complete – the guest...
Days 32 & 33 – 22/23 Jul 19 – Qala

Days 32 & 33 – 22/23 Jul 19 – Qala

by admin | 23 Jul 2019 | Finishing Project, Floor, Plumbing, Triq Il-Mithna, Qala

Days 32 & 33 – 2 busy days switching focus to plumbing and the floor.  Had a great meeting with a friend plumber yesterday who will help when the time comes.   So, all areas that need chasing for taps and water drainage have been done and I’ve put in...
Next Entries »

Recent Posts

  • German Cottage Refurbishment – 12 Jul to 9th Sep 2021
  • Days Lots! Weeks of 9th and 16th Mar 2020 – Qala, the final post
  • Days 179 to 183 – week of 2nd March 2020 – Qala
  • Days 174 to 178 – week of 24th Feb 2020 – Qala
  • Days 165 to 173 – weeks of 10 & 17 Feb 2020 – Qala

Categories

  • Air Con
  • Bathrooms
  • Carpentry
  • Chimney
  • Circuit Breakers
  • Doorways
  • Finishing Project
  • Fireplace
  • Floor
  • Floor screed
  • German Cottage Refurbishment
  • Grouting
  • Insulation
  • Kitchen
  • Light fittings
  • Membrane
  • Pallet to Wine Rack
  • Plastering
  • Plumbing
  • Render
  • Roof
  • Skylight
  • Sockets
  • Terrace
  • Tiling
  • Triq Il-Mithna, Qala
  • Underfloor Heating
  • Window Sills
  • Windows
  • Wiring
Copyright © 2024 Kluvi - all rights reserved.