Days 74 to 76 – 4 to 6 Oct 19 – Qala

Days 74 to 76 – 4 to 6 Oct 19 – Qala

by admin | 6 Oct 2019 | Finishing Project, Floor, Tiling, Triq Il-Mithna, Qala

Days 74 to 76 – More tiling done! The front door area is now complete together with the TV corner in the sitting room.  Bedroom 3 is done apart from the edges which will be done this week. I also managed to build and install a bigger, better and clear plastic...
Days 71 to 73 – 1 to 3 Oct 19 – Qala

Days 71 to 73 – 1 to 3 Oct 19 – Qala

by admin | 3 Oct 2019 | Finishing Project, Tiling, Triq Il-Mithna, Qala, Window Sills

Days 71 to 73 – Quite a productive 3 day period including building 5 temporary windows to protect the apartment from the rain!  Installed 2nd Oct – rain bucketed down that night – not a drop of rain got into the flat. All window sills are now in...
Days 68 to 70 – 26 to 28 Sep 19 – Qala

Days 68 to 70 – 26 to 28 Sep 19 – Qala

by admin | 29 Sep 2019 | Finishing Project, Floor, Tiling, Triq Il-Mithna, Qala

Days 68 to 70 – A really quick post to end a productive week! Tiles now reach all the way to the terrace step, right down the hallway and the master bedroom (driftwood effect tiles) has been started. The focus next week (which for me starts on Tuesday) will be...
Days 65 to 67 – 23 to 25 Sep 19 – Qala

Days 65 to 67 – 23 to 25 Sep 19 – Qala

by admin | 25 Sep 2019 | Finishing Project, Floor, Tiling, Triq Il-Mithna, Qala

Days 65 to 67 – So the last 3 days have been all about tiling and now the kitchen, dining room and sitting room areas are almost complete with a few tiles also starting to make their way down the hallway. The next few days will be dedicated to collecting and...
Days 60 to 64 – 16 to 20 Sep 19 – Qala

Days 60 to 64 – 16 to 20 Sep 19 – Qala

by admin | 20 Sep 2019 | Finishing Project, Plastering, Tiling, Triq Il-Mithna, Qala

Days 60 to 64 – We are plastered! The plastering indoors is now done and rendering on the roof terrace area also done.  The difference plaster makes is extraordinary! The terrace step has been increased in height to accommodate the sliding doors that will be...
Next Entries »

Recent Posts

  • German Cottage Refurbishment – 12 Jul to 9th Sep 2021
  • Days Lots! Weeks of 9th and 16th Mar 2020 – Qala, the final post
  • Days 179 to 183 – week of 2nd March 2020 – Qala
  • Days 174 to 178 – week of 24th Feb 2020 – Qala
  • Days 165 to 173 – weeks of 10 & 17 Feb 2020 – Qala

Categories

  • Air Con
  • Bathrooms
  • Carpentry
  • Chimney
  • Circuit Breakers
  • Doorways
  • Finishing Project
  • Fireplace
  • Floor
  • Floor screed
  • German Cottage Refurbishment
  • Grouting
  • Insulation
  • Kitchen
  • Light fittings
  • Membrane
  • Pallet to Wine Rack
  • Plastering
  • Plumbing
  • Render
  • Roof
  • Skylight
  • Sockets
  • Terrace
  • Tiling
  • Triq Il-Mithna, Qala
  • Underfloor Heating
  • Window Sills
  • Windows
  • Wiring
Copyright © 2024 Kluvi - all rights reserved.