by admin | 16 Nov 2019 | Bathrooms, Finishing Project, Grouting, Tiling, Triq Il-Mithna, Qala
Days 102 to 105 – An interesting week with force 8/9 gales and no windows! Only 4 days worked due to me walking on Wednesday and a guest. However, a busy week. Last weekend we visited the window builder and saw the windows and rear balcony railing. The...
by admin | 2 Nov 2019 | Bathrooms, Finishing Project, Grouting, Plumbing, Tiling
Days 92 to 96 – I took Wednesday off to join the Gozo Wednesday Walkers – something I’ll try and do more frequently going forward. Another busy week in the flat – the weather didn’t permit any further work on the roof so the focus was on...
by admin | 9 Oct 2019 | Finishing Project, Floor, Tiling, Triq Il-Mithna, Qala
Days 77 to 79 – more tiling done – starting to see the end now. The hallway and kitchen corner have been completed, together with the guest bedroom and I’ve just placed the first few tiles in the guest bedroom en-suite. The developer has levelled a...
by admin | 6 Oct 2019 | Finishing Project, Floor, Tiling, Triq Il-Mithna, Qala
Days 74 to 76 – More tiling done! The front door area is now complete together with the TV corner in the sitting room. Bedroom 3 is done apart from the edges which will be done this week. I also managed to build and install a bigger, better and clear plastic...
by admin | 29 Sep 2019 | Finishing Project, Floor, Tiling, Triq Il-Mithna, Qala
Days 68 to 70 – A really quick post to end a productive week! Tiles now reach all the way to the terrace step, right down the hallway and the master bedroom (driftwood effect tiles) has been started. The focus next week (which for me starts on Tuesday) will be...