Days 92 to 96 – 28 Oct to 2 Nov 19 – Qala

Days 92 to 96 – 28 Oct to 2 Nov 19 – Qala

by admin | 2 Nov 2019 | Bathrooms, Finishing Project, Grouting, Plumbing, Tiling

Days 92 to 96 – I took Wednesday off to join the Gozo Wednesday Walkers – something I’ll try and do more frequently going forward. Another busy week in the flat – the weather didn’t permit any further work on the roof so the focus was on...
Next Entries »

Recent Posts

  • German Cottage Refurbishment – 12 Jul to 9th Sep 2021
  • Days Lots! Weeks of 9th and 16th Mar 2020 – Qala, the final post
  • Days 179 to 183 – week of 2nd March 2020 – Qala
  • Days 174 to 178 – week of 24th Feb 2020 – Qala
  • Days 165 to 173 – weeks of 10 & 17 Feb 2020 – Qala

Categories

  • Air Con
  • Bathrooms
  • Carpentry
  • Chimney
  • Circuit Breakers
  • Doorways
  • Finishing Project
  • Fireplace
  • Floor
  • Floor screed
  • German Cottage Refurbishment
  • Grouting
  • Insulation
  • Kitchen
  • Light fittings
  • Membrane
  • Pallet to Wine Rack
  • Plastering
  • Plumbing
  • Render
  • Roof
  • Skylight
  • Sockets
  • Terrace
  • Tiling
  • Triq Il-Mithna, Qala
  • Underfloor Heating
  • Window Sills
  • Windows
  • Wiring
Copyright © 2024 Kluvi - all rights reserved.