Day 22 – Today the kitchen had it’s fibreglass/render coat applied, 3 back boxes were installed for neoStat thermostats (part of the underfloor heating system), and I cut out a chunk of wall to relocate the consumer unit (distribution box) to another part of the kitchen, mainly to keep the integrity of the insulation.

The boys working on the outside of the building for the developer also put in a nice limestone sill on the outside of the dining room shaft – a bit of local stone in a modern breeze block built building.

Tomorrow I’ll chase out and locate the remaining 4 neoStat back boxes and probably make a start on the air conditioning locations.