Day 21 – I’ve had all those light socket back boxes looking at me empty for the last week or so ……. so today I thought I’d do something about it.

All light switches and fittings are now wired!  Slightly harder than wiring the socket points as I had to spend a proportion of the day running up and down a ladder!

Only 3 more “wiring” areas left – the terrace (when we have it waterproofed) and the underfloor heating system (thermostats, heatmiser control centre and the air conditioning final locations.

Tomorrow – will start on the UFH electrics and do some more rendering/fibreglass sheeting.